PETsMART
Since 1993, we have performed several projects for this client. From the installation of 13 new aquarium areas, the construction of 8 new grooming facilities, to miscellaneous specialty work which has spanned 4 States.
The photos below show the task of relocating a series of checkout stands to fit a new store fixture plan. The scope of work included starting at 10:00 pm, moving and modifying the existing millwork, repairing the floor under the previous checkouts, installing new power poles and data lines, and being cleaned and ready for customers by 8:00 am.
A few "work in progress" shots.
(the guy laying down in the first photo works with a Petsmart vendor)
The photo below shows the store, ready for business, at 7:00am.